NEC3 ECSC Payment Application and Employer Assessment Template

NEC3 ECSC Payment Application and Employer Assessment Template

Use this free downloadable template to help you create a payment application and certificate under the NEC3 Engineering and Construction Short Contract (ECSC).

Payment on construction projects is usually regulated by legislation. You must check which legislation applies in your jurisdiction to ensure these templates are suitable.

You can use these NEC3 ECSC templates for the Contractor’s application for payment and the Employer’s assessment as follows:

  • Contractor’s application for payment under clause 50.1
  • Employer’s Assessment under clause 50.4
  • Notify under clause 50.4 of a correction to a payment assessment
  • Notify under clause 51.2 of an assessment of interest on a corrected amount
  • Notify under clause 1.3 of an intention to pay less than the notified sum
  • Notify under clause 1.4 of an intention to suspend performance